In April 2024 the U.S. Army Corps of Engineers (Corps) reaffirmed that it wouldn’t issue a key permit for the Pebble project. The decision culminated a years-long appeals process that … Continued
30
Could Chevron decision affect Pebble mine?
In June 2024, the U.S. Supreme Court overruled a longstanding precedent called “Chevron deference” that had given federal agencies a lot of authority for how they implemented complex laws like … Continued
17
EPA Action Determinative – Pebble Permit Denial Affirmed
Nearly a year ago, the Alaska District of the U.S. Army Corps of Engineers (Corp) was tasked with reviewing portions of its denial of a key Clean Water Act 404 … Continued
27
EPA began 404(c) process to protect Bristol Bay aquatic resources ten years ago
Ten years ago, the U.S. Environmental Protection Agency announced its intent to initiate a process under the Clean Water Act Section 404(c) to restrict discharge of dredged or fill material … Continued
27
Northern Dynasty Minerals and State of Alaska sue over federal protections at Pebble deposit site
In March 2024, both Northern Dynasty Minerals (NDM, owner of Pebble Limited Partnership) and the State of Alaska brought lawsuits against the federal government related to its 2023 decision to … Continued
30
U.S. Army Corps in holding pattern on Pebble
Agency to wait for Supreme Court action on State of Alaska complaint The U.S. Army Corps of Engineers (Corps) Alaska District obtained another extension on its deadline to develop a … Continued
06
Army Corps again pushes back date for determining how it will respond to Pebble appeal review
In April 2024 the Alaska District of the U.S. Army Corps of Engineers (Corps) was given a unique task: look over portions of its November 2020 denial of a Clean … Continued
24
Next steps in the Pebble Army Corps appeal
It’s been nearly three months since the Pacific Ocean Division (POD) of the U.S. Army Corps of Engineers told the Alaska District it would have to revisit portions of its … Continued
20
Connect with agencies on federal and state permitting issues
There are two opportunities for the public to learn more or give input on permitting that affects development projects in Alaska. Public testimony opportunity: Senate Finance Committee The State of … Continued
22
Appeal of permit denial submitted by Pebble Partnership and the State of Alaska
The Pacific Ocean Division (POD) of the U.S. Army Corps of Engineers has received requests for appeal from the Pebble Limited Partnership (PLP) and the State of Alaska, according to … Continued