9
December 2020
If there’s one thing that’s certain about the Pebble project, it’s that nothing is certain. The project has engendered high interest, both for and against, for years. And its extreme swings of fortune have provided both sides extreme highs and lows. The Pebble project has survived several events that could have sunk other projects: major … Continued
25
August 2020
Since Phil St. George first pounded his fist on the Cominco table, demanding more budget to explore the Pebble prospect, the proposed mine has required fierce advocates to push it forward. Opposition has been equally fierce, including the majority of Bristol Bay residents and a broad coalition made up of Alaska Native tribes and corporations, … Continued
25
July 2020
As you read the final EIS for the Pebble project’s 20-year plan, keep in mind you’re reviewing one of the last EIS documents developed under National Environmental Policy Act (NEPA) guidelines in place since 1978. The Pebble project is expected to try and expand operations at some time in the future. Any EIS associated with … Continued
25
July 2020
Wondering what will be in the Joint Record of Decision, the next step in the U.S. Army Corps of Engineers Pebble permitting process? This template helps the Corps develop the ROD. In addition to the final Environmental Impact Statement, the Corps needs to address how the project would comply with laws, regulations and executive orders … Continued
25
July 2020
The U.S. Army Corps of Engineers, the lead federal agency for permit decisions on the Pebble project, has finalized an Environmental Impact Statement (EIS) disclosing impacts of a 20-year mine plan proposed by the Pebble Limited Partnership (PLP) and parent company Northern Dynasty Minerals (NDM). Although it is a significant milestone, the publication of the … Continued
29
May 2020
The U.S. Army Corps of Engineers confirmed in a media advisory last week that it has made a preliminary decision on a Least Environmentally Damaging Practicable Alternative (LEDPA) for the Pebble project. That LEDPA hasn’t been entirely spelled out to the public, but major components mirror those evaluated under “Alternative 3 – North Road Only.” This LEDPA excludes … Continued
23
January 2020
The U.S. Army Corps of Engineers determined last month that it would need to extend the permitting timeline for the Pebble project by 90 days. A Final Environmental Impact Statement (EIS) is due in late June/early July, with a Record of Decision following in Fall 2020. In November and December 2019 the Corps held six … Continued